Short answer: production takes about 45–55 days after payments reach 50% of the order value. Add the time to agree the drawings before that, and ocean freight, customs and local delivery after it. For Australia, New Zealand and other destinations, add sea freight, customs and local delivery to the production time; we estimate the door-to-door total for your port when we quote.
| Stage | Typical time |
|---|---|
| Drawings and finish approval | Depends on how quickly layout, appliances and finishes are settled |
| Production, trial assembly and packing | About 45–55 days after payments reach 50% of the order value |
| Door to door, Australia | Production time plus sea freight, customs and local delivery; we estimate it for your port when we quote |
| Door to door, New Zealand | Production time plus sea freight, customs and local delivery; we estimate it for your port when we quote |
| Other destinations | Ask for a schedule based on your port; see our U.S. import guide for the American sequence |
When ordering custom cabinets from China for an overseas villa, custom home build, or major renovation, the factory production duration is frequently misunderstood. At VSME, the cabinetry brand of Foshan Moyisi Home Furnishings Co., Ltd. (also trading as Moyisi), our published production lead time for custom cabinetry is about 45–55 days after payments reach 50% of the order value.
For an overseas homeowner, builder, or interior designer, the key is knowing what that window covers, what sits outside it, and how to sequence your jobsite trades so goods arrive right when you need them.
The manufacturing clock does not start on the day you first email floor plans or request an initial estimate. The room dimensions, layout, and chosen materials need to be settled before the factory cuts your order.
Day 1 of the 45–55 day window begins when two milestones are reached:
Once those details are confirmed, the workshop can schedule the approved order for production.
To avoid booking site trades too early, think of your cabinetry timeline in three distinct segments rather than a single lump sum:
When planning your site schedule, always treat ocean freight and local delivery as separate windows on top of the factory’s 45–55 day production period.
Yes. While our published production reference is the 45–55 day window, the physical manufacturing steps involved in your chosen door finish will naturally influence pacing on the factory floor:
During the design sign-off stage, our project team will let you know where your specific material combination sits within the production schedule.
Mid-production changes can delay an order. If an appliance model changes or a wall moves after panels are already cut and painted, affected sections must be redesigned, re-machined, and refinished from scratch.
You can keep your delivery moving smoothly with three practical steps:
Working back from a move-in date?
Tell us your target date and send your floor plan on WhatsApp or through the form. We will tell you whether the 45–55 day production window fits and what needs to be decided first.